How to File a Mechanics Lien in Florida

If you have furnished labor, services or materials on a construction project in Florida and have outstanding payments due, then filing a mechanics lien is the instrument you will want to utilize to ensure payment from the property owner. Florida grants lien rights to most project contributors including contractors, subcontractors, suppliers and laborers. However, be wary, Chapter 713, Florida Statutes, provides that certain project contributors must have obtained the proper license upon the date established in the original contract or upon providing services in order to claim lien rights. The following steps will help guide you in filing a valid claim of lien in Florida.

Step 1: Prepare and Serve a Notice to Owner

This Notice to Owner is a form establishing your right to file a claim of lien on the property. Under Florida Statutes, all project contributors mentioned above who do not have direct contracts with the property owner, must prepare and serve this Notice to Owner within 45 days of commencing their work in order to preserve their lien rights. In other words, those who do not have direct contracts with the property owner seeking to file a claim of lien must prepare and serve this Notice of Owner even if you are not owed any money at the time.

Step 2: Prepare Claim of Lien Document

Section 713.08 of the Florida Statutes, provides the proper form and specific requirements to complete the claim of lien document such as: name and address of lienor, statement of labor and materials provided, description of the property, name of property owner, lien amount, proof of service and the proper warning to include at the beginning of the document.

Step 3: Serve the Claim of Lien

Under Florida law, the claim of lien must be served – either in person, by mail or posting the claim on the premises – on the property owner either before recording or within 15 days after recording the lien. Section 713.08(4), Florida Statutes, provides that the failure to serve the claim of lien in the applicable timeframe will render the lien voidable.

Step 4: Record the Claim of Lien

The claim of lien must be recorded in the clerk’s office in the county where the property is located, at any time during the progress of the work or upon completion, but not later than 90 days of the final providing of labor, services or materials by the lienor. If it is not recorded, the lien will be invalid unenforceable.

Although this procedure seems straight forward, Florida’s lien law is complex with many deadlines and nuances you should be aware of. You should consult with one of our experienced and licensed Miami construction attorneys to ensure that your rights are protected.

admin

Recent Posts

Miami condo termination blocked after Florida Supreme Court ruling

Two Roads Development’s efforts to terminate and demolish a Miami condo remains blocked after a…

1 week ago

FL Supreme Court Denies Two Roads Rehearing in Buyout Case

Miami and West Palm Beach-based Two Roads has long planned to develop an Edition Residenceson…

1 week ago

Florida Condo Owners Score Legal Victory in Fight Over $35,000 Special Assessment

The owners and condo board at 1060 Brickell Condos, a two-tower, 45-story luxury high-rise in…

2 weeks ago

Brickell condo owners notch big win in legal battle with association – The Real Deal

Court ordered the association, led by Jacob Kassel. to turn over control, records to winners…

2 weeks ago

Avila v. Biscayne 21: Third District Reinforces Declaration Unanimous Consent Requirements for Condominium Terminations

The Florida Third District Court of Appeal’s revised opinion in Avila v. Biscayne 21 Condo.,…

3 weeks ago

Can a Condominium Association Restrict a Unit Owner’s Attorney from Attending a Meeting?

The issue of whether a condominium association can restrict a unit owner’s attorney from attending…

3 weeks ago